Project Name
Six laning of Kagal-Satara section of NH-48 (old NH-4) [Package – II from km 658.000 to km 725.000] in the State of Maharashtra to be executed on BOT (Toll) mode under Bharatmala Pariyojana
Scope of Work
Widening of Existing 4 lane to 6 lane pavement, Construction of Major and Minor bridges, flyover, underpass, Culverts, road intersections, drains, etc.
Client
National Highways Authority of India (NHAI)
Construction Period
2 years
Length in KM
67 km
Concession Period
18 Years Including Construction Period.
Project Model
BOT (TOLL)
Pavement Classification
Flexible and Rigid Pavement